|
CACV 190 & 191/2025, [2026] HKCA 1656
On Appeal From [2025] HKCFI 1020
IN THE HIGH COURT OF THE
HONG KONG SPECIAL ADMINISTRATIVE REGION
COURT OF APPEAL
CIVIL APPEAL NOS 190 AND 191 OF 2025
(ON APPEAL FROM HCCW NO 316 OF 2018)
________________________
BETWEEN
| |
JOINT AND SEVERAL LIQUIDATORS OF HSIN CHONG CONSTRUCTION (ASIA) LIMITED (IN LIQUIDATION)
|
Applicant
|
| |
and
|
|
| |
WONG PO KEE LIMITED
|
1st Respondent
|
| |
PYROFOE ENGINEERS LIMITED |
2nd Respondent |
| |
KEIO ENGINEERING COMPANY LIMITED |
3rd Respondent |
________________________
(Heard together)
| Before: |
Hon Barma, G Lam and Chow JJA in Court |
| Date of Hearing: |
20 March 2026 |
| Date of Judgment: |
21 September 2026 |
_____________________
JUDGMENT
_____________________
Hon Chow JA (giving the Judgment on behalf of the Court of Appeal):
INTRODUCTION
1. This is the Respondents’ appeal against the order of
Deputy High Court Judge Maria Yuen dated 17 March 2025 (“the Order”) declaring that certain sums
paid to the Respondents (“the Payments”) after the commencement of the winding up of Hsin Chong
Construction (Asia) Limited, in liquidation (“the Company”) constituted dispositions of the properties of
the Company and were void[1] under s 182 of the
Companies (Winding Up and Miscellaneous Provisions) Ordinance, Cap 32 (“the Ordinance”), and ordering the
Respondents to pay the said sums to the liquidators of the Company.
2. The present appeal raises a point of principle, namely,
whether, in a summons issued by the liquidator of a company under s 182 to challenge a disposition of a
property of the company made after the commencement of its winding up, the court has jurisdiction to grant a
declaration that the disposition is void and/or make an order for the return of the property by the transferee
or disponee to the liquidator/the Company.
3. In addition, this appeal raises the substantive issue of
whether the Payments constituted dispositions of the properties of the Company after the commencement of its
winding up, and were therefore void under s 182.
BACKGROUND FACTS
4. The Company was a general and engineering contractor
incorporated in Hong Kong on 13 May 1977. It was ordered to be wound up on 1 June 2020. Joint and
several liquidators (“the Liquidators”) of the Company were appointed on 20 August 2020.
5. Capital Court Limited (“the Employer”), the Company,
and Aedas Limited (“the Architect”) were respectively the employer, main contractor and architect of a
project for the construction of Hong Kong Ocean Park Marriott Hotel at Ocean Park, Hong Kong (“the
Project”).
6. The 1st Respondent (Wong Po Kee Limited), the
2nd Respondent (Pyrofoe Engineers Limited) and the 3rd Respondent (Keio Engineering
Company Limited) were three out of seven nominated sub-contractors (“the NSCs”) for respectively the
plumbing and drainage installation, MVAC and fire services installation, and electrical and ELV installation for
the Project.
7. On 5 December 2016, the Employer and the Company entered into
a written contract for the Project (“the Main Contract”). The Main Contract comprised a number of
contract documents, including the “Conditions” and “Special Conditions of Contract”.
8. Prior to the date of the Main Contract, the Company had, in
August 2016, sent a “letter of acceptance” to each Respondent stating that the Company had been instructed by
the Architect to accept it as the nominated sub-contractor for specified works for the Project. The
relevant sub-contracts (“the Sub-Contracts”) were, however, not signed until 18 December 2018[2]:
(1) Plumbing and Drainage Installation Nominated Sub-Contract between the Company and the
1st Respondent;
(2) MVAC Installation Nominated Sub-Contract and Fire Services Installation Nominated Sub-Contract
between the Company and the 2nd Respondent; and
(3) Electrical and ELV Installation Nominated Sub-Contract between the Company and the
3rd Respondent.
9. The payment procedures under the Main Contract were governed
by Clause 30 of the Conditions (as amended by SCC-23 of the Special Conditions of Contract). In summary,
the payment procedures in the normal course of events would be as follows[3]:
(1) the Company as main contractor would apply to the Architect from time to time for certificates
of payment for works done (including works done by the NSCs);
(2) the Architect would issue certificates stating the amount due to the Company from the
Employer;
(3) the amount of the certificates would be the estimated value of the works properly executed and
of the materials and goods delivered, less (i) any amount which may be retained by the Employer, and (ii)
any instalments previously paid;
(4) the Employer was entitled to retain 10% of the total value of the works, materials and goods
referred to in (3) above (but excluding the amounts in respect of nominated sub-contract works) plus the
retention funds held in respect of the NSCs under the respective sub-contracts; and
(5) the Employer would pay the Company within 28 days after presentation of the certificates, but
it could deduct or set-off sums due from the Company to it.
10. The Main Contract contains provisions concerning payment
to the NSCs. Clause 27 of the Conditions, so far as relevant, provides as follows:
“Nominated Sub-Contractors
…
(a) … Provided that the Architect shall not nominate any person as a sub-contractor … who will
not enter into a sub-contract which provides (inter alia):-
…
(viii) That the Main Contractor shall retain from the sum directed by the Architect as
having
been included in the calculation of the amount stated as due in any certificate issued under clause 30
of
these Conditions in respect of the total value of work, materials or goods executed or supplied by the
Nominated Sub-Contractor the percentage of such value named in the appendix to the Sub-Contract
Conditions
(or, if there be none, in the appendix to these Conditions) …; and that the Main Contractor’s interest
in
any sums so retained (by whomsoever held) shall be fiduciary as trustee for the Nominated Sub-Contractor
(but without obligation to invest) and that the Nominated Sub-Contractor’s beneficial interest in such
sums
shall be subject only to the right of the Main Contractor to have recourse thereto from time to time for
payment of any amount which he is entitled under the sub-contract to deduct from any sum due or to
become
due to the Nominated Sub-Contractor; and that if and when such sums or any part thereof are released to
the
Nominated Sub-Contractor they shall be paid in full.
(b) The Architect shall direct the Main Contractor as to the estimated value of the work,
materials or goods executed or supplied by a Nominated Sub-Contractor included in the calculation of the
amount stated as due in any certificate issued under clause 30 of these Conditions and shall forthwith
inform the Nominated Sub-Contractor in writing of the amount of the said estimated value. The sum
representing such estimated value shall be paid by the Main Contractor to the Nominated Sub-Contractor
within fourteen days of receiving payment from the Employer against the Architect’s certificate less
only
(i) any retention money which the Main Contractor may be entitled to deduct under the terms of the
sub-contract, and (ii) any sum to which the Main Contractor may be entitled in respect of delay in
completion of the Sub-Contract Works or any part thereof.
(c) Before issuing any certificate under clause 30 of these Conditions, the [Main
Contractor
shall furnish the Architect][4] reasonable
proof
that all amounts (less due retentions) included in the calculation of the amount stated as due in
previous
certificates in respect of the total value of the work, materials or goods executed or supplied by any
Nominated Sub-Contractor have been duly discharged, and if the Main Contractor fails to comply with [the
same][5] and unless he shall produce to the
Architect in writing
(i) reasonable cause for withholding or refusing to discharge such amounts as are due, and
(ii) reasonable proof that he has so informed such Nominated Sub-Contractor,
the Architect shall issue a certificate to that effect and thereupon the Employer may
himself
pay such amounts to any Nominated Sub-Contractor concerned and deduct the same from any sums due or to
become due to the Main Contractor.
…
(f) Neither the existence nor the exercise of the foregoing powers nor anything
else
contained in these Conditions shall render the Employer in any way liable to any Nominated
Sub-Contractor.”
11. As earlier mentioned, the Sub-Contracts were entered into
on 18 December 2018. For the purpose of the present appeal, save in respect of Clause 11(h) of the
Sub-Contracts, the other terms or conditions are not material. The effect of Clause 11(h) of the
Sub-Contracts, as noted by the Judge, is that the Company’s interest in the Retention Money, whether included in
the amounts retained by the Employer under the Main Contract and held by it or held by the Company, is fiduciary
in nature, and the Retention Money is held by the Company as trustee for the NSCs (but without any obligation to
invest)[6].
12. In or about April 2017, the 2nd Respondent
became aware that the Company was in financial difficulty. On 27 April 2017, it sent a letter to the
Employer requesting that payment for sub-contract works executed be paid directly to it instead of via
the Company.
13. Apparently, there was no reply from the Employer to the
2nd Respondent’s letter of 27 April 2017. However, the Employer did discuss with the
Company the question of direct payment to the NSCs. On 12 May 2017, the Employer and the Company entered
into a supplementary agreement (“the Supplementary Agreement”)[7] to provide for direct payment to the NSCs in respect of sub-contract works executed by
them. The following provisions of the Supplementary Agreement are material for the purpose of the present
appeal:
“(1) This Supplementary Agreement varies and supplements the terms of the Main Contract…
(2) In consideration of the provisions stated in Clause (3) below, the Employer agrees to
directly pay to all Nominated Sub-Contractors (commencing from and including the interim certificate No.13
by the Architect) and deduct the sums so paid from any sums due or become due to the Main Contractor
(excluding the amounts payable or paid to the Nominated Sub-Contractors).
(3) In consideration of the provisions stated in Clause (2) above, the Main Contractor agrees
the following:
(i) Payment Mechanism
The payments in respect of any works, materials or goods under the Nominated Sub-Contracts
shall be made in full amount based on the terms and conditions in the respective Nominated Sub-Contracts
without any adjustments for charges, set-off, and the like between the Main Contractor and the Nominated
Sub-Contractors.
After the Architect issues an interim certificate stating the amounts due to the respective
Nominated Sub-Contractors, the Nominated Sub-Contractors should present the notification to the
Employer,
together with the written confirmation of payment to be received from the Employer, and be entitled to
payment within 28 days from the presentation of the Certificate.
The Main Contractor agrees that the sums paid by the Employer directly to the Nominated
Sub-Contractors shall be deemed to have been paid via the Main Contractor and waives any claims against
the
Employer that he has not received any amount in connection with the payments to the Nominated
Sub-Contractors.
…
Except for the Main Contractor’s obligation regarding payments to the Nominated
Sub-Contractors, such direct payment to the Nominated Sub-Contractors by the Employer shall not
discharge
the Main Contractor from any obligation to the Nominated Sub-Contractors under the Contract.”
(For ease of reference, the 4 sub-paragraphs in Clause 3(i) above will hereinafter be respectively referred to as
“Clause 3(i)(a)”, “Clause 3(i)(b)”, “Clause 3(i)(c)” and “Clause 3(i)(d)” of
the Supplementary Agreement.)
14. On 15 May 2017, the Company issued letters to each of the
NSCs (including the 1st, 2nd and 3rd Respondents) headed “Employer’s Direct
Payment to Nominated Sub-Contractors (Commencing from and including the Interim Certificate No.13)” (“the
Direct Payment Letters”). The Direct Payment Letters state as follows:
“Further to our recent discussion with the Employer, we hereby write to inform you of the
revised payment procedure as agreed and confirmed with the Employer as follows:
1. Starting with the interim certificate no. 13, interim payments as certified by the Architect
to the Nominated Sub-Contractors (NSCs) shall be made directly by the Employer to the NSCs;
2. After the Architect issues an interim certificate stating the amounts due to the respective
NSCs, the NSCs should present the notification to the Employer, together with the written confirmation of
payment to be received from the Employer, and be entitled to payment within 28 days from the presentation of
the Certificate; and
3. The payments in respect of any works, materials or goods under the Nominated Sub-Contracts
shall be made in full amount based on the terms and conditions in the respective Nominated Sub-Contracts
without any adjustments for charges, set-off, and the like between the Main Contractor and the NSCs.
Please note that such direct payment to the NSCs by the Employer shall not discharge the NSCs
from any obligation to the Main Contractor under the Nominated Sub-Contracts.”
15. The Direct Payment Letters were copied to the Employer and
the Architect. Each of the 1st, 2nd and 3rd Respondents countersigned a
copy of the Direct Payment Letter to signify that it agreed to and accepted the terms thereof.
16. On 2 October 2018, the Architect issued a certificate of
practical completion of the Project.
17. On 5 November 2018, a winding-up petition was presented
against the Company in HCCW 316/2018. On 1 June 2020, the Company was ordered to be wound up by
Harris J.
Accordingly, the winding up of the Company is deemed to have commenced on 5 November 2018.
18. Between 7 November 2018 and 17 August 2020, the Employer
made the Payments directly to the Respondents pursuant to Interim Certificates Nos IP31, 32, 34 and 36 to 40 in
accordance with the arrangements in the Supplementary Agreement/Direct Payment Letters:
|
Nominated Sub-Contractors |
Dates of Payment |
Retention Monies (HK$) |
Non-Retention Monies (HK$) |
|
The 1st Respondent |
7.11.2018 – 30.9.2019 |
2,449,000 |
8,047,000 |
|
The 2nd Respondent |
7.11.2018 – 17.8.2020 |
4,966,500 |
17,604,000 |
|
The 3rd Respondent |
7.11.2018 – 17.8.2020 |
3,590,500 |
17,779,000 |
19. In July 2023, the Liquidators demanded the Respondents to
return the aforesaid sums received by them from the Employer. The demands were not met.
20. On 10 July 2024, the Liquidators issued a summons (“the
Section 182 Summons”) against the Respondents seeking, inter alia:
(1) a declaration that the Payments in the total sum of HK$54,436,000, or such other sum as found
by the court, made by the Employer to the Respondents after the commencement of the winding up of the
Company were void under s 182 of the Ordinance; and
(2) the 1st Respondent, the 2nd Respondent and the 3rd Respondent
do return and pay the respective sums of HK$10,496,000, HK$22,570,500 and HK$21,369,500, or such other sums
as found by the court, to the Liquidators within 7 days from the date of the order to be made.
THE DECISION
21. At the hearing of the Section 182 Summons before the
Judge, the Respondents contended that s 182 of the Ordinance had no application to the Payments on the
following grounds:
(1) there was a variation of the Main Contract as a result of a tripartite agreement between the
Employer, the Company and the Respondents evidenced by the Supplementary Agreement which had the effect of
disposing of the Company’s right to receive the Payments from the Employer in respect of the sub-contract
works under the Main Contract (“the Variation Ground”);
(2) there was an assignment by the Company to the Respondents of its right to receive the Payments
from the Employer effected by the Direct Payment Letters (“the Assignment Ground”);
(3) there was a novation of the Main Contract to the effect that the Company’s right to receive
the Payments from the Employer under the Main Contract (the Company’s chose) would be extinguished, and
replaced by a newly created right acquired by the Respondents against the Employer (“the Novation
Ground”);
(4) estoppel by convention (“the Estoppel Ground”); and
(5) there was a trust over the Retention Monies in favour of the NSCs (“the Trust Ground”).
22. On 17 March 2025, the Judge gave her decision (“the
Decision”) rejecting the Variation, Assignment, Novation and Estoppel Grounds advanced by the
Respondents, but upholding the Trust Ground subject to the Company’s right to set-off against the Retention
Monies liquidated damages and contra-charges claimed by the Employer in respect of works done by the
Respondents.
23. The Judge considered, based on the judgment of the Court
of Final Appeal in Re Hsin Chong Construction Co Ltd (2021) 24 HKCFAR 98 and as illustrated in the
judgment of the Court of Appeal in Chevalier (HK) Ltd and Anor v The Joint Liquidators of Right Time
Construction Co Ltd (in Liquidation) [1990] 2 HKLR 223, that for the purpose of the application of s 182
of the Ordinance, the focus should be on the relevant property and its disposition[8]. On the facts of the present case, the Judge held that:
(1) The relevant property was the right (a chose in action) that the Company had to receive money
from the Employer, including money for works done by the Respondents, which right was converted into the
funds in the Payments.
(2) The relevant disposition was the making of the Payments to the Respondents at a time when the
Company’s winding up had commenced. The fact that the Company had authorised the Payments before the
commencement of winding up, that they might have been made under contract, and the Company’s motive when so
agreeing, were immaterial.
(3) Accordingly, the making by the Employer of the Payments to the Respondents after the
commencement of the winding up of the Company was caught by s 182[9].
24. The Judge rejected the Variation Ground for, inter
alia, the following reasons: (i) there was no evidence of any tripartite agreement amongst the Employer,
the Company and the Respondents (who were not included as parties to the Supplementary Agreement, and apparently
were not even aware of its terms as they had not been given a copy of it), (ii) the terms of the Supplementary
Agreement did not support the Respondents’ contention that it had the effect of disposing of the Company’s right
to receive payments from the Employer in respect of the sub-contract works under the Main Contract, and (iii)
the context of the Supplementary Agreement did not lead to the conclusion that the Employer thereby entered into
a new, direct contractual relationship with the Respondents, with the Company abrogating its rights under the
Main Contract.
25. The Judge rejected the Assignment Ground for the following
reasons: (i) a mere mandate or authority was not enough to effect an assignment, (ii) for there to be an
assignment, it must be plain that the assignor (the Company) intended to divest itself of the chose and vest it
in the assignee (the Respondents), (iii) it was clear from the terms of the Supplementary Agreement that the
Company did not intend to divest itself of the right to payment from the Employer, and (iv) what it intended to
effect was a “payment mechanism”, as per the specific heading of the Supplementary Agreement, or a “revised
payment procedure”, as per the Direct Payment Letters, and that was what the Respondents were “entitled” to.
26. The Judge rejected the Novation Ground because a novation
occurred only where there was consent by all three parties, but it was clear there was no intention on the part
of the Employer and the Company that the latter’s right to payment from the former under the Main Contract (the
Company’s chose) would be extinguished, and replaced by a newly created right acquired by the Respondents
against the Employer, between whom there were not even discussions, let alone an agreement.
27. The Judge rejected the Estoppel Ground for the following
reasons: (i) the Respondents’ contention ignored the public policy underpinning s 182 as explained by the Court
of Final Appeal in Hsin Chong and illustrated in Chevalier, (ii) when a statute was enacted
on grounds of general public policy, an estoppel could not be asserted against it, at least not in circumstances
where a validation order would not be granted, and (iii) the Respondents had not sought a validation order in
the present case[10].
28. In respect of the Trust Ground, the Judge held that a
trust existed in respect of the Retention Monies in favour of the Respondents as stipulated in Clause
27(a)(viii) of the Conditions and Clause 11(h) of the Sub-Contracts, and thus the Respondents were entitled to
the Retention Monies, subject to the Company’s right of set-off for any liquidated damages and contra-charges
claimed by the Employer in respect of works done by the Respondents (to be ascertained).
29. Accordingly, the Judge:
(1) declared that the payment of the Non-Retention Monies made by the Employer to the Respondents
after the commencement of the winding up of the Company was void under s 182 of the Ordinance (“the
Declaration”);
(2) ordered each Respondent to pay to the Liquidators the respective Non-Retention Monies that it
had received within 28 days from the date of the order (“the Non-Retention Monies Payment Order”);
and
(3) ordered each Respondent to pay to the Liquidators the respective Retention Monies that it had
received to be held by the Liquidators in a separate trust account for each Respondent pending finalization
of the final account between the Employer and the Company in respect of the Project and any consequential
set-off (“the Retention Monies Payment Order”, collectively “the Payment Orders”).
THE APPEALS
30. The 1st and 2nd Respondents and the
3rd Respondent have each lodged an appeal against the Order.
31. The 1st and 2nd Respondents’ amended
notice of appeal in CACV 190/2025 (“R1-2 ANOA”) contains 6 grounds:
(1) Grounds 1 to 4 challenge the Judge’s rejection of the Variation, Assignment, Novation and
Estoppel Grounds;
(2) Ground 5 challenges the Retention Monies Payment Order; and
(3) Ground 6 contends that the court had no jurisdiction to grant the Declaration or make the
Payment Orders.
32. The 3rd Respondent’s notice of appeal in
CACV 191/2025 (“R3 NOA”) contains 6 substantive grounds:
(1) Grounds 2 to 5 challenge the Judge’s rejection of the Variation, Assignment, Novation and
Estoppel Grounds[11];
(2) Ground 6 challenges the Non-Retention Monies Payment Order; and
(3) Ground 7 challenges the Retention Monies Payment Order.
33. On 20 February 2026, the 3rd Respondent issued
a summons seeking leave to amend its notice of appeal. The main additional point which the 3rd
Respondent wishes to raise is that the Judge should not have made the Payment Orders on the ground that under
the rule in Ex p James [1874] LR 9 Ch App 609, “no high minded person in the position of the liquidators
would wish to enforce strictly their legal rights or to retain any payments recovered under s.182”[12].
THE JURISDICTION ISSUE
34. Section 182 of the Ordinance states as follows:
“In a winding up by the court, any disposition of the property of the company, including things
in action, and any transfer of shares, or alteration in the status of the members of the company, made after
the commencement of the winding up, shall, unless the court otherwise orders, be void.”
The 1st and 2nd Respondents’ arguments
35. Mr Jonathan Chang, SC (on behalf of the 1st and
2nd Respondents) puts at the forefront of his arguments in this appeal the contention that, in
an application under s 182 made by summons, the court has no jurisdiction to make a declaration that a
deposition of a company’s property made after the commencement of its winding up is void, or an order that the
property disposed of shall be returned to the company.
36. Mr Chang submits that the only order which s 182 empowers
the court to make is to “otherwise order”, ie a “validation order”. Nothing in the Ordinance or the
Companies (Winding-up) Rules, Cap 32H (“the Winding-up Rules”) provides for a liquidator (or
a company in liquidation) to issue a civil claim for recovery of any property disposed of under a transaction
invalidated by s 182. Mr Chang says that the invalidation of a disposition of a company’s property and the
recovery of the property disposed of are two distinct matters. Section 182 is concerned with
invalidation, not recovery. The latter is governed, not by statute, but by the general law, specifically
the law of restitution. See Re J Leslie Engineers Co Ltd (in liquidation) [1976] 1 WLR 292, 298A-D;
Hollicourt (Contracts) Ltd v Bank of Ireland [2001] Ch 555, §22; Re MKG Convenience Ltd (in
liquidation) [2019] BCC 1070, §42, and Skandinaviska Enskilda Banken AB v Conway [2020] AC 1111,
§§59-74.
37. Mr Chang further submits that the Liquidators’
restitutionary claim within the winding up process in the present case is not a mere technical defect; it has
caused real and substantial injustice to the 1st and 2nd Respondents. In view of the
way in which the Section 182 Summons was framed (ie as an application under s 182), the parties’ focus was on
the question of whether the Payments made in accordance with the arrangement in the Supplementary
Agreement/Direct Payment Letters were caught by s 182. He contends that even if the Payments are caught by
s 182 (or s 182 is engaged), it does not necessarily follow that the Company would be entitled to recover the
Payments from the 1st and 2nd Respondents in a restitutionary claim had the claim been
properly pursued by way of a general civil action, for the following reasons.
38. First, in a claim for unjust enrichment, it must be shown
that the claimant has suffered a loss through his provision of benefit to the defendant (Investment Trust
Companies v Revenue and Customs Commissioners [2018] AC 275, §§43-44; and TFL Management Services Ltd
v Lloyds TSB Bank plc [2014] 1 WLR 2006, §51). There is, however, no loss suffered by the Company
corresponding to the Payments received by the Respondents, because it would still have a contractual claim
against the Employer for the outstanding amounts.
39. Second, Mr Chang says that the 1st and
2nd Respondents may also be able to raise a “change of position” defence, in that (i) they have
changed their position in good faith in reliance on the Company’s representation that they would be paid
directly by the Employer; (ii) the Company has obtained a benefit in having the Project completed on time,
thereby discharging its contractual obligations under the Main Contract; and (iii) it would be inequitable for
the Company, acting through the Liquidators, to mount a restitutionary claim for the recovery of the Payments
against the Respondents. Mr Chang recognizes that there are different views taken in Commonwealth
jurisdictions on whether a defence of change of position is available to resist a restitutionary claim in
respect of a transaction invalidated by insolvency legislation, and draws the Court’s attention to Rose v AIB
Group (UK) plc [2003] 1 WLR 2791, §§30 and 41; Officeserve Technologies Ltd v Annabel’s (Berkeley
Square) Ltd [2019] Ch 103, §§37-43; contrast with Re MKG, §§62-69; Changtel Solutions UK Ltd.
v G4S Secure Solutions (UK) Ltd [2023] BCC 143, §§109-174; and Skandinaviska, §§113-117.
Nevertheless, he submits that even in jurisdictions which have adopted a more restrictive approach, it would
appear that a “change of position” defence (in a more attenuated form) is available where it would be
inequitable to allow the restitutionary claim to proceed: see Re MKG, at §§67-70.
40. According to Mr Chang, the incorrect course adopted by the
Liquidators in the present case has resulted in essential issues going towards the validity of the claim (if
any) not being addressed at all, and the 1st and 2nd Respondents have been deprived of
relevant procedural safeguards applicable to general civil actions, such as seeking an order of security for
costs against the Company.
41. Mr Chang acknowledges that the jurisdictional point was
not taken before the Judge, but argues that the point should nevertheless be entertained by this Court because:
(i) jurisdiction cannot be conferred by the consent of the parties; and (ii) the court is bound to inquire into
an issue which goes to its jurisdiction irrespective of whether the parties have raised it.
The Liquidators’ arguments
42. Ms Audrey Eu, SC (on behalf of the Liquidators) submits
that s 182 renders a post-petition disposition void ab initio, with the consequence that the company has
never been divested of the beneficial ownership of the property purportedly disposed of. Hence, the
Liquidators’ claim for recovery of the property disposed of is proprietary, not in unjust enrichment. Mr
Chang’s restitutionary analysis is therefore misplaced. So is his reliance on the Privy Council’s decision
in Skandinaviska, because it was a case relating to voidable preference under s 145(1) of the Cayman
Companies Law, whereas s 182 renders the relevant disposition void ab initio.
43. Ms Eu refers the Court to Goode on Principles of
Corporate Insolvency Law (5th ed), at §13-141, where Sir Roy classifies s 127 of the Insolvency Act 1986
(the English equivalent of s 182 of the Ordinance) as a provision rendering a post-petition disposition void
unless authorised or validated by the court, and ss 238, 239 and 423 of the Insolvency Act as provisions
for the reversal of the effect of a transaction. Ms Eu submits that the “voidance” provision in s 127 is
conceptually distinct from the “restitutionary avoidance” regimes under ss 238, 239 and 423. Ms Eu also
points out that Sir Roy makes it clear at §13-142 that recovery under s 127 is a “pure property remedy”,
not a “restitutionary remedy”, so that the defences available under the law of restitution will not apply.
In respect of the defence of change of position, Sir Roy states: “To allow change of position as a defence
would be to give preferential treatment to the defendant without there necessarily being any corresponding
benefit to the other creditors. … it is hard to see why the court should be expected to engage in the
complexities of the change of position defence when its powers of authorisation or validation provide all
the flexibility that is needed.”
44. Re J Leslie Engineers Co Ltd does not assist the
1st and 2nd Respondents. Oliver J’s observations that invalidation and recovery
are “two logically distinct matters” and that the appropriate remedy “has to be determined by the
general law” address analytical sequence, not procedural forum. Oliver J himself made a recovery
order within the same proceedings (304G-H).
45. Ms Eu submits that the above analysis is confirmed by
settled authority on the court’s jurisdiction to order repayment: see Chevalier, at
229F-G; Bank of East Asia Ltd v Rogerio Sou Fung Lam [1988] 1 HKLR 181, at 193C; and Re AGI
Logistics (Hong Kong) Limited [2016] 5 HKLRD 737, at §37 (cited by the Court of Final Appeal in
Hsin Chong, fn 34). She also points out that the same jurisdictional objection was
rejected by
Deputy High Court Judge Le Pichon in Re Hsin Chong Construction (Asia) Ltd (in liquidation)
[2025] 2
HKC 521, at §§49-63.
46. Finally, Ms Eu argues that the 1st and
2nd Respondents’ complaint that they have been deprived of a chance to plead to the Company’s
restitutionary claims for the recovery of the Payments (including advancing restitutionary defences where
appropriate), and other procedural safeguards applicable to general civil actions (such as an application for
security for costs against the Company) does not help them, as they did not ask for, or file evidence to
justify, the need for pleadings or a separate trial.
Court has jurisdiction to grant the Declaration and make the Payment Orders
47. We do not accept the 1st and 2nd
Respondents’ jurisdictional objection. The fallacy of their argument lies in the premise that the court’s
powers to grant relief in a summons issued by a liquidator under s 182 are derived entirely from, or
confined to what is provided by, that section. On its face, s 182 provides for the consequence of various
specific types of transaction made after the commencement of the winding up of a company, namely, (i)
disposition of the property of the company (including things in action), (ii) transfer of shares of the company,
and (iii) alteration in the status of the members of the company. Such transactions are rendered “void” by
the operation of s 182, unless the court otherwise orders. It does not follow, however, that in a summons
issued by a liquidator under that section, the court has no power to make consequential orders or grant
consequential relief upon finding that the relevant disposition of the company’s property is void. There
is no doubt that the court does have jurisdiction, in an ordinary civil action commenced by the liquidator, to
grant proprietary and/or restitutionary remedies (as appropriate) in respect of a disposition of the company’s
property rendered void by the operation of s 182. We can see no valid reason why the court would lose its
jurisdiction to grant such remedies in an application properly before the court brought by a liquidator by way
of summons. Under s 200(3) of the Ordinance, a liquidator may apply to the court in manner prescribed for
directions in relation to any particular matter arising under the winding up, and under r 7(2) and (3) of the
Winding-up Rules, every application by a liquidator to the court for directions in relation to any particular
matter arising under the winding up shall be made by summons in chambers. Nothing in the Ordinance or the
Winding-up Rules takes away the court’s jurisdiction to grant proprietary and/or restitutionary remedies in an
application made by a liquidator under s 182 by way of summons.
48. If the 1st and 2nd Respondents’
argument is correct, it would mean that the court would have no jurisdiction even to make a declaration that the
relevant disposition is void. If so, it would be difficult to think of any situation where a liquidator
may properly make an application under s 182 by way of summons. It is, however, the experience of the
members of this Court that applications under s 182 made by way of summons seeking declaratory and/or other
substantive relief are not uncommon, and such applications are regularly entertained by the courts without
question. For example, declaratory and other substantive relief were granted in (i) Chevalier,
at 225E-G; (ii) AGI Logistics [2015] 4 HKLRD 300, at §§1 and 39 (Anthony Chan J, as he then
was), affirmed by the Court of Appeal ([2016] 5 HKLRD 737); and (iii) Hsin Chong, at §42 (in that case,
the s 182 summons was issued by the recipient of the company’s property seeking a validation order[13], but the Court of Final Appeal eventually
made a declaration that the relevant agreement and dispositions were void).
49. The same jurisdictional objection was raised before, but
rejected by, Deputy High Court Judge Le Pichon in Re Hsin Chong Construction (Asia) Ltd (in Liquidation)
[2025] 2 HKC 521. There, an application was made by the Liquidators by summons under s 182 for a
declaration that certain payments totalling HK$11,295,350 made by Employer after the commencement of the winding
up of the Company to Cogent Spring Limited (“Cogent Spring”) were void, and for an order that Cogent
Spring returned and/or paid the said sum to the Liquidators. One of the arguments raised by Cogent Spring
to resist the payment order sought by the Liquidators was that (i) the Court had no jurisdiction to grant a
payment order because s 182 merely avoided dispositions, leaving recovery to be determined by the general law;
and (ii) the Company only parted with the right of action against the Employer, hence, the remedy is confined to
restoring that right and not immediate payment. Deputy High Court Judge Le Pichon referred to the
judgment of the Court of Appeal in AGI Logistics, at §37, and held that it supported the view that where
a payment was determined to be a disposition and that disposition was void under s 182, recovery of the amount
should be viewed as correcting the wrongful disposition of the company’s property which the court had power to
order. She also pointed out that a payment order was made in Re Leslie Engineers Co Ltd, at
304G-H[14]. In Deputy High Court Judge
Le Pichon’s view, those cases were clear authorities that the Court had jurisdiction to grant an immediate
payment order. We agree.
50. It is not with disrespect to counsel that we do not
propose to analyse the many authorities cited by them concerning the true nature of the relief which a
liquidator may be entitled to seek in respect of a disposition which is rendered void by the operation of s
182. We do not do so because, in our view, the answer to the jurisdictional objection raised by the
1st and 2nd Respondents does not lie in whether the Liquidators’ claim for recovery of the
Payments is proprietary or restitutionary. It is not the 1st and 2nd Respondents’
argument that the court may grant proprietary, but not restitutionary, remedies in a summons issued by the
liquidator under s 182. Their argument is a simple one: the only remedy, or order, that the court
may make in an application under s 182 is to “otherwise order”, ie a validation order. On this argument,
the court would have no jurisdiction to grant either proprietary, or restitutionary, remedies, or declaratory
relief, even when the court comes to the conclusion that the relevant disposition is void under s 182.
51. On the question of the true nature of the relief that may
be granted to a liquidator in respect of a disposition found to be void under s 182, we would merely
observe that the liquidator may be entitled to claim proprietary, or restitutionary, remedies, or both,
depending on the circumstances. For example, in the case of a transfer of a company’s landed property to a
transferee after the commencement of its winding up, the liquidator would have a proprietary claim against the
transferee for the reconveyance of the landed property. In the situation where the property disposed of is
a sum of money in the company’s a bank account, the liquidator would, in principle, have both a proprietary and
restitutionary claim against the recipient. However, if the recipient has in the meantime paid the money
received to a bona fide purchaser for value without notice, the liquidator would no longer be able to
bring any proprietary claim against the recipient, but should still be able to advance a restitutionary claim
against the recipient (subject to such defences as may be available to such a claim).
52. As regards Mr Chang’s complaints that the 1st
and 2nd Respondents have suffered real and substantial injustice because of the way in which the
Section 182 Summons was framed, which it is said focused the parties’ attention on the question of whether the
Payments were caught by s 182 and has resulted in essential issues going towards the validity of the claim not
being addressed at all (such as whether the Company has suffered any loss, and whether the 1st and
2nd Respondents are able to set up a defence of change of position), we do not consider that these
complaints are germane to the question of whether the court has jurisdiction to grant the Declaration or make
the Payment Orders. In this regard, it is important to bear in mind the distinction between the situations
where (i) the court has no power to make an order or type of order, and (ii) the court declines to exercise its
jurisdiction to make the order or type of order. The former goes to jurisdiction, in the strict sense,
while the latter goes to the exercise of jurisdiction. Mr Chang’s complaints may be relevant to the
question of whether the court should exercise the jurisdiction to grant the Declaration or make the Payment
Orders, but are not relevant to the question of whether the court has jurisdiction to grant such relief in the
first place.
53. In any event, we do not accept the validity of Mr Chang’s
complaints. Insofar as the framing of the Section 182 Summons is concerned, the summons expressly sought
both a declaration and orders for payment of specified sums to the Liquidators. The 1st and
2nd Respondents should not be in any doubt that the Liquidators were seeking immediate payment
orders against them. It was up to the 1st and 2nd Respondents to raise any specific
defence to the payment orders sought by the Liquidators, and adduce appropriate evidence to support such
defence. If they considered that the issues of whether the Company had suffered any loss, or whether they
were able to set up a defence of change of position, could not or should not be disposed of on the basis of
affidavit evidence alone, they could have sought appropriate directions from the court, and the court would have
ample case management powers to address their concern, such as ordering the deponents to attend court for
cross-examination, ordering issues to be stated and tried, or ordering pleadings to be exchanged and discovery
to be given. Apparently, the 1st and 2nd Respondents were content to proceed with
the substantive hearing of the Section 182 Summons on the basis of the existing evidence. In the absence
of any specific defence being raised to the Liquidators’ claim for immediate payment of the sums received by the
Respondents (save in relation to the Retention Monies), the Judge was entitled to make an unconditional order
for immediate payment of the Non-Retention Monies upon being satisfied that the relevant dispositions were
void. It is now too late for Mr Chang’s complaints to be entertained at this stage. The same comment
applies to Mr Chang’s further complaint that the 1st and 2nd Respondents have been
deprived of relevant procedural safeguards applicable to general civil actions (such as seeking an order of
security for costs against the Company). These are matters which the 1st and 2nd
Respondents ought to have raised with the Judge, but failed to do so.
54. In all, we reject the jurisdictional objection raised by
the 1st and 2nd Respondents.
DISPOSITION OR DIVESTMENT OF THE COMPANY’S RIGHT TO RECEIVE PAYMENT FROM THE EMPLOYER UNDER THE
SUPPLEMENTARY AGREEMENT
55. Both the 1st and 2nd Respondents and
the 3rd Respondent contend in their respective appeals that the Judge erred in failing to find that
there was an effective disposition or divestment by the Company of its right to receive payments in respect of
the sub-contract works from the Employer under the Main Contract prior to the commencement of the winding up of
the Company. Their arguments are based primarily on the true construction of the Supplementary Agreement,
although some reliance is also placed on the Direct Payment Letters and other matters. In terms of legal
analysis, if the contention of the Respondents is correct, there would be a “variation” of the Main Contract in
relation to the Company’s right to receive payments from the Employer in respect of the sub-contract works,
although the Respondents have also put their cases on the basis of “assignment” and/or “novation”.
The Respondents’ arguments
56. The 1st and 2nd Respondents’
arguments that the Judge erred in holding that the Supplementary Agreement did not have the effect of disposing
of the Company’s right to receive payments from the Employer in respect of the sub-contract works under the Main
Contract are fully set out in Ground 1 of R1-2 ANOA. Those arguments have been adopted by Mr Chang in his
submissions to the Court[15].
57. The 1st and 2nd Respondents argue
that the Judge erred in her understanding of Golden Sand Marble Factory Ltd v Easy Success Enterprises Ltd
and Anor [1999] 2 HKC 356. The relevant test for the purposes of s 182 in the context of this case
is not whether there was a tripartite agreement, but whether “the main contractor loses any right under the main
contract it might have had otherwise to insist that payment be made through it”: see Golden Sand, at
360I-361B. The 1st and 2nd Respondents contend that the Company lost such right
in respect of the Payments because the Supplementary Agreement, on its true construction, had the effect of
disposing of any right that the Company might otherwise have to receive payments from the Employer in respect of
the sub-contract works.
58. In relation to the true construction of the Supplementary
Agreement, the 1st and 2nd Respondents argue that:
(1) The Judge misconstrued, or misunderstood the purpose of, Clause (3)(i)(c) of the Supplementary
Agreement (“… sums paid by the Employer directly to the Nominated Sub-Contractors shall be deemed to have
been paid via the Main Contractor …”). That provision was simply to ensure that the Company
would not be able to pursue the Employer for sums paid by the Employer directly to the NSCs.
(2) The words “[shall] be entitled to payment” in Clause (3)(i)(b) of the Supplementary
Agreement vested the legal right to receive payments as certified by the Architect in respect of the
sub-contract works in the NSCs. This construction is supported by Clause (2) of the Supplementary
Agreement, which states inter alia that “the Employer agrees to directly pay to all Nominated
Sub-Contractors (commencing from and including the interim certificate No.13 by the Architect)”.
(3) The Judge erred in holding that the “entitlement” of the NSCs referred to the
implementation of a payment mechanism only (Decision, §33). This reading goes against the natural and
ordinary meaning of Clause (3)(i)(b), which simply refers to the NSCs’ entitlement “to
payment” without any qualification thereto.
(4) The Judge also erred in holding that the Supplementary Agreement only added an alternative
route to direct payment under Clause 27(c) of the Conditions (Decision, §34). The Supplementary
Agreement required the Employer to pay the NSCs directly, instead of giving the Employer a discretion to pay
them in some specified circumstances.
(5) The Judge was wrong in her view that the words “without any adjustments for charges,
set-off and the like between the Main Contractor and the Nominated Sub-Contractors” in Clause
3(i)(a) of the Supplementary Agreement did not support the Respondents’ case that the payments made by the
Employers ceased to be the property of the Company. The fact that the Company could no longer assert
any charges or set-off against the payments made pursuant to the Supplementary Agreement shows that such
payments were no longer the property of the Company.
(6) The purpose of Clauses (2) and (3)(i)(c) of the Supplementary Agreement was to ensure that the
Company would not pursue the Employer for the sums paid to the NSCs. The fact that the words
“deduct” and “waives any claims” are used in those clauses indicates that the Company no
longer
had any entitlement to the sums payable and/or paid to the NSCs under the Supplementary Agreement.
59. The 1st and 2nd Respondents point
out that the interim certificates subsequently issued were entirely consistent with the above proper
understanding of the Supplementary Agreement, in that they deducted from the valuation of the works completed,
the amounts to be paid directly to the NSCs, and thus certified only the net amount as due to the Company.
60. The 1st and 2nd Respondents further
argue that the Judge failed to place sufficient weight on the context from which the Supplementary Agreement
arose. In particular, the Judge did not sufficiently address the fact that: (i) on 27 April 2017, one of
the NSCs wrote to the Employer and requested that direct payments be made in light of the Company’s financial
situation; (ii) around 2 weeks later, on 12 May 2017, the Supplementary Agreement was entered into; and
(iii) 3 days later, on 15 May 2017, the Direct Payment Letters were issued. In light of the quick
succession of the aforementioned events, the Judge should have found that (1) the Company had abrogated its
right under the Main Contract, and (2) the Supplementary Agreement and the Direct Payment Letters evidenced a
clear agreement between the Employer, the Company and the NSCs that the NSCs would be entitled to receive direct
payments from the Employer in respect of the sub-contract works.
61. Lastly, the 1st and 2nd Respondents
complain that the Judge erred in not considering the Contracts (Rights of Third Parties) Ordinance,
Cap 623. The fact that it was not a stand-alone point does not mean that it did not require
consideration. The 1st and 2nd Respondents have a right to seek payments directly
from the Employer under the Supplementary Agreement by virtue of the Contracts (Rights of Third Parties)
Ordinance. In particular, (i) the Supplementary Agreement purported to confer the benefit of payment of
money by the Employer on the 1st and 2nd Respondents, (ii) they were identified by the
term “Nominated Sub-Contractors” in the Supplementary Agreement, and (iii) there is nothing to rebut the
presumption that the terms of the Supplementary Agreement were intended to be enforceable by them. Had the
Judge found that the NSCs were entitled to enforce the terms of the Supplementary Agreement, she should have
concluded that the Supplementary Agreement extinguished the right of the Company to receive payment in respect
of the sub-contract works. There could not be simultaneously an obligation on the Employer to pay monies
due to the NSCs both to the NSCs and to the Company. Equally, there could not simultaneously be a right
vested in both the NSCs and the Company to receive the monies: see Golden Sand, at 360E-F.
Moreover,
the fact that the NSCs were entitled to enforce the terms of the Supplementary Agreement would have obviated the
need to find any tripartite agreement between the Employer, Company and NSCs.
62. Under Ground 2 of R3 NOA, the 3rd Respondent
argues that the Judge fell into error when she found that the terms of the Supplementary Agreement did not or
were insufficient to divest the Company of its right to payment from the Employer, for the following reasons:
(1) The Judge was wrong to have considered the Supplementary Agreement in isolation or in
conjunction with the terms of the Main Contract, or to have taken a construction that rendered the
Supplementary Agreement superfluous to the already existing agreed terms of payment.
(2) In construing the Supplementary Agreement, the Judge failed to take into account or properly
take into account two other supplementary agreements[16], the Direct Payment Letters, and the intended fourth supplementary agreement
pending execution by the Employer.
(3) The Judge was wrong to find that the relevant payments by the Employer could not be excluded
from s 182 in the absence of a tripartite agreement, and to construe the Supplementary Agreement merely as
an agreement to vary the payment mechanism.
(4) The Judge was wrong to find that the terms of the Supplementary Agreement affirmed the right
of the Company to receive payments from the Employer. She should instead have found that it
facilitated the meeting of the conditions of payment under the Main Contract so as to divest the Company of
its entitlement to receive the same.
(5) Under the circumstances of this case, and on a proper construction of the various agreements
and letters mentioned above, there was clearly a tripartite arrangement among the Employer, the Company and
the NSCs to exclude the relevant payments from s 182 for the purpose of facilitating the performance and
eventual completion of the works under the Project in the event of the winding up of the Company.
The above arguments are elaborated in the written submissions of Mr Jason Wong (for the 3rd
Respondent) [17], which it is not necessary to
repeat in this Judgment.
The Liquidators’ arguments
63. Ms Eu argues that the Supplementary Agreement only varied
the payment mechanism, but did not create a contractual relationship between the Employer and the NSCs absent
tripartite agreement, and cannot displace pari passu without a trust: see Keating on Construction
Contracts (12th ed), at §13-051; Goode on Principles of Corporate Insolvency Law, at
§8-12; and British Eagle International Airlines Ltd v Compagnie Nationale Air France [1975] 1 WLR 758, at
780G–781B.
64. Ms Eu further argues that the Supplementary Agreement was
a bipartite agreement between the Employer and the Company. The Respondents were not parties, did not
participate in the negotiation and were not provided with a copy. It is unrealistic to suggest that the
parties intended, by an agreement of which the Respondents had no knowledge, to extinguish the Company’s
entitlement in the Respondents’ favour.
65. In respect of various provisions of the Supplementary
Agreement relied upon by the Respondents, Ms Eu submits that:
(1) The phrase “be entitled to payment” in Clause 3(i)(b) of the Supplementary Agreement
must be construed contextually. It is under the sub-heading “Payment Mechanism”, and describes
how
and when the NSCs would receive payment (upon presentation of the certificate, within 28 days), not whether
the underlying right to the monies belonged to them.
(2) The words “deemed to have been paid via the Main Contractor” in Clause 3(i)(c) of the
Supplementary Agreement preserved the Company’s legal entitlement to payment from the Employer as of right,
notwithstanding that the physical mechanism bypassed its bank account. The “entitlement” of the
NSCs referred to the implementation of the new payment mechanism, understood against the rest of the
document. It was not a freestanding legal right to the underlying debt. The Supplementary
Agreement added an alternative route without extinguishing the Company’s underlying right (Decision, at
§§32–34).
(3) The waiver provision in Clause 3(i)(c), under which the Company “waives any claims against the
Employer that he has not received any amount in connection with the payments to the Nominated
Sub-Contractors”, presupposed a subsisting right. If the Company’s entitlement to payment had been
extinguished, there would be nothing to waive (Decision, at §40).
(4) The deduction mechanism under Clause 2 of the Supplementary Agreement provides that the
Employer shall “deduct the sums so paid from any sums due or become due to [the Company]”. This
language is only intelligible if sums remained “due” to the Company. If the Company had dropped
out of the picture, there would be nothing from which to deduct (Decision, §38). Clause 3 also secured
the Company’s consent and waiver in return for the Employer’s direct payments under Clause 2. This
presupposes the Company’s subsisting entitlement – otherwise it would have had nothing to give by way of
consideration.
66. In respect of the Respondents’ complaint that the Judge
erred in focusing on the question of whether there was a tripartite agreement amongst the Employer, the Company
and the NSCs, Ms Eu contends that the Judge’s analysis of whether there was a tripartite agreement was part of
the substantive analysis of the true meaning and effect of the Supplementary Agreement. In Golden
Sand, the employer, main contractor and sub-contractor all agreed that payment would be made directly to
the sub-contractor; Findlay J held at 360I that this extinguished the main contractor’s right to insist that
payment passed through it. In Hitachi Plant Engineering & Construction Co Ltd v Eltraco
International Pte Ltd [2003] SGCA 38, the Singapore Court of Appeal reconciled Golden Sand with
non-tripartite cases, holding that where the nominated sub-contractors’ entitlement to direct payment remained
“contingent upon the Architect’s exercise of their discretion”, the nominated sub-contractors did not
have any right to receive payment (§§35-36). The same analysis applies here. Under Clause 27(c) of
the Conditions, the NSCs’ entitlement to direct payment is contingent upon the Architect’s decision whether to
certify direct payment; and even then, the Employer “may” pay directly - it is not obliged to do
so. The NSCs have no right to insist on direct payment from the Employer. Nothing in the
Supplementary Agreement displaces the condition precedent to the Company’s entitlement under Clause 30 of the
Conditions and Clauses 11 and 13 of the Sub-Contracts. The Supplementary Agreement, as found by the Judge,
added an alternative route for payment.
67. As for the Respondents’ contention that the Supplementary
Agreement imposed a mandatory obligation inconsistent with the Company’s entitlement, Ms Eu submits that this
contention conflates the obligation to adopt a particular payment route with the extinction of the underlying
right. The Supplementary Agreement mandated direct payment as the alternative payment mechanism; it did
not recognise the Respondents as having a proprietary right to the payments. The argument that the no
“adjustments for charges, set-off” clause demonstrates the payments ceased to be the Company’s property
is answered by the Judge’s observation at §36.1-36.2 of the Decision that the mechanism enabled funds to be paid
quickly, and it defied commercial sense for a financially distressed company to abandon all set-off
rights. The 3rd Respondent’s submissions pointing out that a direct payment may result in
overpayment on the part of the Company[18]
reinforces the Judge’s view that the Company preserved its entitlement and was left to “settle accounts” with
the NSCs later (Decision, §36.1).
68. Lastly, Ms Eu says that the Direct Payment Letters were
informative; they did not record any agreement to confer the Respondents any new rights.
69. In all, Ms Eu submits that the Judge was correct in her
view that the Supplementary Agreement did not dispose of the Company’s right to receive the Payments from the
Employer under the Main Contract.
Applicable principles
70. As pointed out by the Judge at §25 of the Decision, when
considering the applicability of s 182 to any given fact situation, the focus should be on the relevant
“property” of the insolvent company and its “disposition”.
71. The leading authority on the true interpretation of s 182
is the judgment of the Court of Final Appeal in Hsin Chong. In that case, Hsin Chong and Build King
entered into a Joint Venture Agreement in 2013 for the purpose of tendering for and carrying out a Government
construction project in Kowloon. In 2016, the joint venture was awarded a Government contract for the
project, with Hsin Chong holding a 65% interest in the joint venture and Build King holding the remaining
35%. The Joint Venture Agreement contained a mechanism dealing with insolvency. Clause 17 allowed
one party to exclude the other from further participation in the joint venture if the other party became
insolvent. The party exercising the clause would become the “Continuing Party”, while the insolvent party
would become the “Defaulting Party”. If Clause 17 was invoked, the Defaulting Party would be excluded
from further participation in the management of the joint venture, the contract, and the profits arising from
it, and the Continuing Party would take over the benefits of the Defaulting Party in the joint venture. In
2017/2018, Hsin Chong came under serious financial difficulties. In August 2018, a winding up
petition was presented by a creditor against Hsin Chong. In December 2018, Build King invoked Clause
17. Under that clause, an accounting exercise would have to be carried out at the completion or
termination of the project to determine whether Hsin Chong was entitled to any accrued profit up to the date of
exclusion after deducting its share of losses and other costs arising from its default (referred to in the
judgment as Hsin Chong’s “residual rights”). In December 2018, Hsin Chong and Build King entered into a
supplemental agreement, whereby Build King agreed to acquire Hsin Chong’s residual rights for a sum ($53.6
million) to be paid in two instalments. The supplementary agreement specified that the sum was to be paid
into an account of Cogent Spring, a wholly owned subsidiary of Hsin Chong. This payment arrangement was
important because Hsin Chong’s own bank accounts had been frozen, and it was originally contemplated that the
money received from Build King would be used to settle Hsin Chong’s outstanding Mandatory Provident Fund
contributions and staff wages. Build King proceeded to pay the first instalment into Cogent Spring’s
account, and part of the money was in fact used for some other purposes. Build King did not pay the second
instalment, and made an application for a retrospective validation order under s 182 in respect of the payment
of the first instalment. The Court of Final Appeal held that the supplemental agreement and the
dispositions made thereunder were void by reason of s 182. The reasoning which led to that conclusion can
be found in the following passages in the joint judgment of Ribeiro and Fok PJJ (with whom the other
members of the Court of Final Appeal agreed):
“[32] The concern of section 182 is with the disposition of a company’s property made after
commencement of the winding up. If a transaction amounts to such a disposition, it is void unless the
court
orders otherwise. And as we have seen, in deciding whether to validate the disposition, the court
regards
the interests of the general body of creditors as of central importance.
[33] It is therefore important to identify correctly the Company’s property and the disposition
in question. Here, the Company’s residual rights plus incidental interests under the JVA constituted
the
initial property concerned. The Company agreed to sell them to Build King for the consideration of
$53.6
million, payable in two instalments. So the residual and incidental rights were converted into a
contractual
chose in action consisting of a right to payment of that consideration which was the Company’s
property. By
entering into the SA with its clause 5, the Company and Build King agreed that that payment should not be
made into the Company’s coffers (to circumvent the freezing of its bank accounts) but should instead be made
to Cogent Spring, a different entity within the Group. In performing that agreement, a disposition of
a
chose in action with the value of $20 million, the first instalment, took place. Section 182 became
applicable and rendered the SA and payment made thereunder void unless the Court otherwise orders.
…
[35] … If as a result of that payment, the Company’s property is transferred or dissipated so
that the interests of the general body of creditors are prejudiced, it matters not that the transfer or
dissipation is wrapped in contractual clothing. It is still a disposition which attracts section 182
and its
prejudicial effect on the unsecured creditors prevents the transaction from being validated…
[36] The question of whether a disposition has taken place is one of substance and not
form. As
was explained by HH Judge Paul Matthews (sitting as an additional judge of the High Court) in Officeserve
Technologies Ltd (in Liquidation) v Anthony-Mike, whether a disposition occurs is judged by what
happens to the value of a company’s asset as a result of the transaction in question…
…
[40] … As indicated above, the concern of section 182 is to preserve the Company’s property for
proper distribution under the statute, applying to dispositions made after commencement of the winding
up.
The section does not concern itself with the parties to the transaction and does not require it to be shown
that such parties were involved in any breaches of duty before the disposition is rendered presumptively
void…
[41] … The effect of holding the SA void would be that the Company could revert to a
claim against Build King for the value of its residual rights under the JVA as determined on a final
accounting. It is uncertain how that amount would compare to the sum of $53.6 million agreed to under
the SA.”
In short, the relevant “property” was Hsin Chong’s right to receive the payment of $53.6 million (a contractual
chose in action) from Build King as consideration for the sale of the residual rights to Build King, and there
was a “disposition” of that property, namely, the first instalment of the payment under clause 5 of the
supplementary agreement which provided that the money was to be paid to Cogent Spring, a different entity from
Hsin Chong.
72. Another authority which elucidates the concepts of
“property” and “disposition” in s 182 is the judgment of the Court of Appeal in Chevalier. The
facts of that case were as follows. Reality was the employer under a construction contract for a project
at Tuen Mun with Right Time as the main contractor. Chevalier and Regent were nominated sub-contractors
under that main contract. In April 1987, the architect for the project issued a payment certificate,
certifying that a sum of money, which included various amounts payable to the nominated sub-contractors, was due
for payment under the main contract. Right Time wrote to Reality confirming that it had no objection to
Reality paying the nominated sub-contractors directly in respect of that and subsequent certificates.
Reality duly paid Chevalier and Regent directly on 29 April 1987, but the cheques were not cleared until 25 May
1987, by which time the winding up of Right Time was deemed to have commenced because the petition was presented
on 1 May 1987. On an application brought by liquidators of Right Time to challenge the payments under s
182, the Court of Appeal held that the payments constituted dispositions of the properties of Right Time and
were void, for the following reasons (at 229C-G):
“ … Ignoring for the moment the effect of s.182, when Reality (with the authority of Right
Time) paid its own money to each appellant, the position was that Reality was entitled to, and no doubt did
in its books, debit the Right Time account to the extent of the payments made to each of the appellants.
This reduction in the debt owed by Reality to Right Time was a reduction made with the authority of Right
Time and amounted to a disposition of Right Time’s property within the meaning of s.182.
Furthermore there was also a disposition of Right Time’s property effected when Reality made
the payments to each of the appellants [Chevalier and Regent] because, as between Right Time and Reality on
the one hand and each appellant on the other hand, Reality had acted, in effect, as the agent of Right Time
and paid the sums of money to which Right Time was entitled (under the main contract) to the appellants in
partial discharge of Right Time’s debt to each of them.
Section 182 retrospectively renders both these dispositions void and produces the
result that the liquidators of Right Time became entitled to recover the amount of the relevant payments
from Reality, on the basis that the reduction in Reality’s debt to Right Time under the main contract was
made without lawful authority, or from the appellants as money paid to them by Reality to the use of Right
Time. We consider that the liquidators acted properly in making their first claim on the appellants who had
received the money rather than on Reality…”
It can be seen that the Court of Appeal analysed the factual situation as involving two relevant dispositions of
the properties of Right Time, either of which would be sufficient to trigger the operation of s 182: (i) the
first disposition occurred when the debt owed by Reality to Right Time for works carried out under the main
contract (a contractual chose in action vested in Right Time) was reduced as a result of payments made by
Reality to Chevalier/Regent, and (ii) the second disposition occurred when sums of money to which Right Time was
entitled were paid by Reality (as agent for Right Time) to Chevalier/Regent in partial discharge of Right Time’s
debt to each of them.
73. The last authority that we should deal with is the
judgment of Findlay J in Golden Sand relied upon by Mr Chang. The facts of that case can briefly be
stated as follows. The plaintiff (Golden Sand) was a nominated sub-contractor in a construction project.
The second defendant (Pentad) was the main contractor while the first defendant (Easy Success) was the
employer. The main contract contained the usual provision for payments to Golden Sand to be made through
Pentad, and also the standard clause that permitted Easy Success, if the architect for the project issued the
required certificate, to pay Golden Sand directly and deduct the relevant sum from sums due to Pentad (clause
27(c)). In about March 1995, prior to the practical completion of the project (which occurred in May
1996), an agreement was reached between all interested parties that future payments in relation to the nominated
sub-contractors’ works would be paid directly by Easy Success to the respective nominated sub-contractors, and
not through Pentad. On 19 June 1996, Pentad was wound up by the court. In issue was whether the
final sum
(including retention money) which the architect certified on 30 May 1997 as being due from Easy Success to
Golden Sand in respect of sub-contract works carried out by the latter was the property of Pentad.
Findlay J found in favour of Golden Sand, holding that Pentad had no property right in the money at the
time of its liquidation. The learned judge reasoned as follows (at 360C-361B and 363F-H):
“ So there is no doubt that the plaintiff and both defendants agreed that payments due to the
plaintiff would be made directly to the plaintiff. Mr Carolan says that this agreement between the parties
was only that the payment mechanism be varied and this was not binding on the liquidator. He draws attention
to the statement by the first defendant that ‘there is no change as to the contractual relationship and the
rights and obligations there-arised between us and Pentad under the main contract and between Pentad and
yourselves under the nominated sub-contract’, but this cannot be taken literally. There cannot be
simultaneously an obligation on the first defendant to pay the money due to the plaintiff both to the
plaintiff directly under the March agreement and to the second defendant under the main contract, and there
cannot simultaneously be a right vesting both in the plaintiff under the March agreement and in the second
defendant under the main contract to receive the money. Clearly, what the first defendant was saying was
that, subject to what we have agreed, the contracts will remain the same. It was saying – ‘We have all
agreed that I will make payments directly to the plaintiff, but, otherwise, the contractual relationships
will remain the same.’
In the case where an employer acts unilaterally under cl 27(c) and pays a nominated
sub-contractor directly and deducts this payment from money due to the main contractor, it must be that, if
the main contractor is liquidated after that payment is made, no right of property in that money was vested
in the main contractor on the date of winding up. Where, however, the liquidation happens before the
employer has made the payment, it must be, on principle, that the right to receive the payment was still
vested in the company in liquidation at the time of winding up.
But that is academic to this case. Here, there was no unilateral decision by the first
defendant under cl 27(c). In the case before me the employer, the main contractor and the nominated
subcontractor agreed that payments would be made directly to the nominated subcontractor a long time before
the liquidation. So, whatever the position may be where there is a unilateral act under cl 27(c), where
there is an agreement such as here the sub-contractor acquires an enforceable right to have the payments
made directly to him, and the main contractor loses any right under the main contract it might have had
otherwise to insist that payment by made through it. Here, there is no question of the employer exercising a
discretion to pay the nominated subcontractor directly. It is a matter of rights under the agreement of
March 1995.
…
… Here, there is no basis on which it could be suggested that, at the date of liquidation, the
second defendant had any right at all to receive the money in respect of the work of the nominated
subcontractors. It is, in my view, not arguable on the facts of this case that any property in this money
was vested in the second defendant at the date of liquidation.”
74. It can be seen that Findlay J took the view that the
agreement which the parties entered into in March 1995 prior to the winding up of Pentad had the effect of
divesting Pentad’s right to receive payment in respect of works carried out by Golden Sand from Easy Success
under the main contract, and thus such right could no longer be regarded as the “property” of Pentad as at the
date of its liquidation.
75. Ms Eu points out that in that case, Easy Success, Pentad
and Golden Sand all agreed that payment would be made directly by Easy Success to Golden Sand; in other
words, there existed a tripartite agreement. This observation is correct as far as its goes, but this
feature does not seem to us to be critical to the decision of Findlay J. At the bottom of the learned
judge’s decision was the question of whether the right to receive payment from Easy Success was still vested in
Pentad at the time of its liquidation such that the right could be regarded as the property of Pentad. The
absence of a tripartite agreement was not determinative of that question. This is because Pentad’s right
to
receive payment in respect of works carried out by Golden Sand from Easy Success was a matter of bilateral
contract (ie the main contract) between Pentad and Easy Success. The bilateral contract could, in
principle, be varied by the mutual agreement of Pentad and Easy Success without the need for participation by
any third party. If the true meaning or effect of the variation agreement was to take away the right of
Pentad to receive certain payment from Easy Success, there would be no reason in principle why such agreement
was not effective to divest Pentad of its right to receive such payment. Whether there was a tripartite
agreement involving Golden Sand which would enable it to enforce the variation agreement in its own right should
not, in principle, affect the validity of the variation agreement entered into between Easy Success and Pentad.
The Company’s right to receive the Payments was effectively disposed of or divested under the
Supplementary Agreement
76. In our view, the Company’s right to receive payments in
respect of sub-contract works carried out by the NSCs from the Employer under the Main Contract had been
effectively disposed of or divested under the Supplementary Agreement prior to the commencement of its winding
up. It follows that the Payments were not caught by s 182 of the Ordinance.
77. Prior to the making of the Supplementary Agreement, the
Company was entitled to receive payments from the Employer in respect of sub-contract works carried out by the
NSCs (including the 1st to 3rd Respondents) under the Main Contract. However,
upon the making of the Supplementary Agreement, the relevant amounts would no longer be due, or payable, to the
Company. Instead, the Employer is entitled, and bound (as a matter of contract vis-à-vis the
Company), to make payment to the NSCs directly. Unlike Clause 27(c) of the Conditions, which confers on
the Employer a discretion to make direct payments to the NSCs in certain specified circumstances, the
Supplementary Agreement obliges the Employer to make direct payments to the NSCs. This obligation flows
from Clause (2) of the Supplementary Agreement, which provides that in consideration of what the Company agrees
under Clause (3) (executory consideration), the Employer “agrees” to directly pay all NSCs commencing from
a specified interim certificate by the Architect, and deduct such sums so paid from any sums due or which may
become due to the Company. This new payment arrangement is binding on both the Company and the
Employer. After the making of the Supplementary Agreement, the Company would have no valid ground to
complain about payments made by the Employer directly to the NSCs, or deductions made by the Employer of
corresponding amounts from any sums otherwise due or which may become due to the Company. Conversely, if
the Employer should, for any reason, refuse to make payment to the NSCs in accordance with Clause (3), the
Company whould, in principle, be entitled to bring an action against the Employer to enforce the Supplementary
Agreement. The Supplementary Agreement is a valid contract supported by consideration moving from both
sides. It was plainly intended to be binding on both the Employer and the Company. We can see no
reason why the Supplementary Agreement should not be given effect in accordance with its plain terms.
78. Since the Supplementary Agreement was entered into on
12 May 2017, by the time of the commencement of the winding up of the Company (5 November 2018), the
relevant “property” (namely, sums which might be certified as due for sub-contract works carried out by the
NSCs) was no longer the property of the Company. There was no disposition of the Company’s property made
after the commencement of the winding up which would be caught by s 182.
79. Although the facts of the present case are different from
those in Golden Sand, the reasoning of Findlay J is equally applicable to the present situation. As
earlier mentioned, Ms Eu seeks to rely on the judgment of the Singapore Court of Appeal in Hitachi to
explain why Golden Sand is not applicable to the present case. The facts in Hitachi are very
different from those in Golden Sand or the present case. In Hitachi, the main contractor was
placed under judicial management pursuant to an order of the Singapore court, and a scheme of arrangement was
approved, under which it was provided that “[t]he realisation from the [main contractor’s] assets (mainly
accounts receivable from completed projects) after meeting the costs of realisation and administration shall be
paid entirely to the creditors” in certain specified manner. There was no relevant agreement for the
disposition or divestment of the main contractor’s right to receive payment from the employer. The
architect received a request from some nominated sub-contractors for direct payment by the employer, and the
architect later issued a certificate of direct payment to the nominated sub-contractors. Thereupon, the
scheme administrators brought proceedings to restrain the employer from effecting direct payments to the
nominated sub-contractors, and for an order for the nominated sub-contractors to authorise the employer to
effect such payments due to them to the main contractor instead. The Singapore Court of Appeal upheld the
scheme administrators’ claim, holding that while the pari passu principle did not extend to schemes of
arrangement, the nominated sub-contractors did not have a right to the payments when the scheme was approved and
sanctioned (§86). The Singapore Court of Appeal distinguished Golden Sand at §§35-36 of its
judgment:
“[35] … There, the employer, contractor and sub-contractor came to an agreement prior to the
insolvency of the contractor that the employer would make direct payments to the sub-contractor. These
direct payments were allowed by the Hong Kong Court of First Instance on the basis that there was a right to
them by virtue of the agreement between the parties. Here, [the main contractor, employer] and the
NSCs did
not enter into an express agreement to elevate the NSCs’ entitlement to the direct payments to a right that
had to be protected by the express terms of the Scheme.
[36] The [nominated sub-contractors’] entitlement to direct payment under cl
31(1)(b) of the Main Contract is contingent upon the Architects’ exercise of their discretion to certify
direct payment to the NSCs. The Architects only exercised that discretion on 22 June 2002. As
such, we find that the [nominated sub-contractors] did not have a right to receive direct payment at the
time the Scheme was approved on 4 October 2000, some 18 months prior to the Architects’ exercise of their
discretion. Therefore, while we agree with counsel that there is a general principle that the rights
of creditors can only be affected by an express term in a scheme of arrangement, that principle does not
apply on the facts of the present appeals because the [nominated sub-contractors] did not have a right to
those payments at the time the Scheme was proposed and sanctioned.”
80. We do not consider that the decision in Hitachi
assists the Liquidators in the present case. It is correct that on the facts of Golden Sand, there
was a tripartite agreement, to which the nominated sub-contractor (Golden Sand) was a party, and the nominated
sub-contractor had acquired a contractual right to receive direct payment from the employer (Easy Success) under
the tripartite agreement. However, as mentioned at §75 above, central to Findlay J’s analysis was the fact
that the main contractor’s right to receive payment from the employer had been divested or disposed of prior to
the commencement of the winding up of the main contractor. Whether there was such divestment or
disposition did not necessarily depend on the existence of a tripartite agreement amongst the employer, main
contractor and nominated sub-contractor.
81. The Liquidators’ emphasis on the sub-heading “Payment
Mechanism” of Clause (3)(i) of the Supplementary Agreement is misplaced. The new payment arrangement under
the Supplementary Agreement may properly be described as a “payment mechanism”. However, what is important
is not the description, or label, given to the payment arrangement, but whether the payment arrangement is
binding on the parties.
82. In respect of the deeming provision (“… the sums paid
by the Employer directly to the Nominated Sub-Contractor shall be deemed to have been paid via the Main
Contractor”), and the waiver provision (“the Main Contractor … waives any claims against the Employer
that he has not received any amount in connection with the payments to the Nominated Sub-Contractors”),
in Clause 3(i)(c) which the Liquidators heavily rely on, we consider them to be equivocal. As submitted by
the Respondents, these provisions can reasonably be read and understood as provisions designed to ensure that
the Company would not be able to pursue the Employer for sums paid directly to the NSCs, and are consistent with
the view taken that the Company’s right to receive payments in respect of sub-contract works carried out by the
NSCs from the Employer under the Main Contract was divested, or disposed of, upon the making of the
Supplementary Agreement.
83. Neither do we consider the deduction mechanism in
Clause (2) of the Supplementary Agreement relied upon by Ms Eu supports the Liquidators’ argument that the
right to receive the Payments remained vested in the Company. It seems to us that Clause (2) merely makes
it clear that the sums payable to the Company under the Main Contract would be reduced by the sums paid by the
Employer directly to the NSCs pursuant to the arrangement in the Supplementary Agreement. Otherwise, the
Employer would be liable to make payment twice (once to the Company and the other to the NSCs). This
plainly could not have been the intention of the parties to the Supplementary Agreement.
84. Before we leave this part of the judgment, we wish to
briefly deal with a few other points raised by the Respondents in their submissions.
(1) We do not read much into the no “adjustments for charges, set-off” provision in Clause
3(i)(a) of the Supplementary Agreement relied upon by the 1st and 2nd Respondents in
support of the contention that the right to receive the Payments was no longer the property of the
Company. It seems to us that the purpose of this provision was to fix the amount to be paid by the
Employer to the NSCs directly, leaving adjustments for charges and set-off to be dealt with
separately. This arrangement makes obvious commercial sense bearing in mind that adjustments for
charges and set-off could take a long time to resolve, while the NSCs were anxious to receive early payments
in view of the Company’s known financial difficulties.
(2) In relation to the issue of tripartite agreement, the Judge was fully aware of the chronology
in respect of the 2nd Respondent’s letter to the Employer (27 April 2017), the Supplementary
Agreement (12 May 2017), and the Direct Payment Letters (15 May 2017). The Judge nevertheless held
that there was no evidence of any tripartite agreement[19]. We do not consider that there is any sufficient basis for this Court to
intervene in this finding of the Judge, and we reject the Respondents’ case of a tripartite agreement
amongst the Employer, the Company and the NSCs as regards the right to receive payments in respect of the
sub-contract works from the Employer under the Main Contract.
(3) We also do not accept the 1st and 2nd Respondents’ criticism that the
Judge erred in failing to consider the applicability of the Contracts (Rights of Third Parties)
Ordinance. As mentioned by the Judge at §27.2 of the Decision, the Respondents’ former leading counsel
clarified at the hearing that his argument based on that Ordinance was not a “stand-alone point”, and only
“buttressed” his other arguments in support of the Variation Ground. Since the Judge rejected all
other arguments advanced by the Respondents in support of the Variation Ground, it was a matter for the
Judge whether to consider the applicability of the Contracts (Rights of Third Parties) Ordinance for the
sake of completeness. Further, as noted by the Judge at §43 of the Decision, the Contracts (Rights of
Third Parties) Ordinance only deals with the right to sue. As it is, we do not consider the question
of whether the NSCs have a direct right to sue on the Supplementary Agreement to be essential in the
determination of whether the Payments constitute dispositions of the Company’s property for the purpose of
s 182 of the Ordinance.
OTHER GROUNDS OF APPEAL
85. Having reached the above conclusion, it becomes
unnecessary for us to consider the other grounds of appeal raised by the Respondents. For the sake of
completeness, we shall briefly state our views on those grounds.
86. In respect of the Assignment Ground and Novation Ground[20], Mr Chang accepts that those grounds are
dependent on the Court finding that the Company had divested itself of the right to receive the Payments from
the Employer, while Mr Wong did not develop any substantive argument on those grounds in his written or oral
submissions. It seems to us that neither the Supplementary Agreement nor the Direct Payment Letters
purport to be, or can reasonably be read as, an assignment of the Company’s right to receive the Payments from
the Employer to the NSCs, or an agreement to assign such right, while the Novation Ground is unsustainable in
the absence of any tripartite agreement entered into amongst the Employer, the Company and the NSCs to effect a
substitution or replacement of the relevant elements of the Main Contract concerning the Company’s right to
receive the Payments from the Employer by a new contract.
87. In respect of the Estoppel Ground[21], we agree with the Judge that the notion of estoppel is
incompatible with the public policy underpinning s 182 of the Ordinance: see Kok Hoong v Leong Cheong Kweng
Mines Ltd [1964] AC 993, at 1015-1016:
“ The respondent has invoked in support of its defence a principle which appears in our law in
many forms, that a party cannot set up an estoppel in the face of a statute… Similarly, there is, in most
cases, no estoppel against a defendant who wishes to set up the statutory invalidity of some contract or
transaction upon which he is being sued, despite the fact that by conduct or other means he would otherwise
be bound by estoppel: see In re Bankruptcy Notice, in particular per Atkin L.J.
It does not appear to their Lordships that the principle invoked is confined to transactions
that have been made the subject of legislation or that, where legislation is in question, the bare
prescription that a transaction is to be void or unenforceable is sufficient by itself to justify the
principle’s application…
It has been said that the question whether an estoppel is to be allowed or not
depends on whether the enactment or rule of law relied upon is imposed in the public interest or ‘on grounds
of general public policy’ (see In re A Bankruptcy Notice, per Atkin L.J.). But a principle as widely stated
as this might prove to be rather an elusive guide, since there is no statute, at least public general
statute, for which this claim might not be made. In their Lordships’ opinion a more direct test to apply in
any case such as the present, where the laws of moneylending or monetary security are involved, is to ask
whether the law that confronts the estoppel can be seen to represent a social policy to which the court must
give effect in the interests of the public generally or some section of the public, despite any rules of
evidence as between themselves that the parties may have created by their conduct or otherwise…”
88. As a matter of principle, it seems to us to be clear that
parties cannot by agreement contract out of the legal consequence of s 182 if the relevant disposition is caught
by that section. If such avoidance cannot be achieved by contract, we do not see how it can be achieved by
an estoppel based on a course of conduct of the parties.
89. In respect of the 3rd Respondent’s challenge to
the Non-Retention Monies Payment Order[22], if
the relevant dispositions were caught by s 182, we can see no basis to interfere with the Judge’s order for the
return of the Non-Retention Monies to the Liquidators. It would appear that the contention that the Judge
should not have made the Non-Retention Monies Payment Order because of the 3 matters identified in Ground 6 of
R3 NOA is a new point not taken before the Judge[23]. If it was a point taken before the Judge and it was not dealt with in the Judge’s
Decision, one would expect the 3rd Respondent to raise as a ground of appeal the complaint that the
Judge failed to deal with the point in her decision. There is no such ground of appeal in R3 NOA (or in
the 3rd Respondent’s draft amended notice of appeal). We do not consider the 3rd
Respondent should be permitted to raise this point for the first time in the Court of Appeal, since it is a
point which depends on an evaluation of the evidence and involves an exercise of discretion, which ought to be
undertaken by the Judge at first instance. In any event, we do not consider that they are sufficient to
cause us to intervene in the Judge’s decision to make the Non-Retention Monies Payment Order:
(1) The suggestion that validation orders, had they been applied for, would have been granted, is
nothing more than a bare assertion. As observed by the Judge, the Respondents had not sought any
validation order in the present case (by the time of the hearing below)[24].
(2) We do not see any sound basis for the 3rd Respondent’s contention that the direct
payment arrangement having been agreed between the Employer and the Company prior to the winding up, the
risk of the Payments being caught by s 182 ought to be borne by the Employer.
(3) Neither are we persuaded that the court should exercise a discretion in favour of the
Respondents (ie not ordering the return of the Non-Retention Monies) given the time taken by the Liquidators
to take action to recover the Payments. There is no evidence that the Liquidators have been guilty of
unreasonable or excessive delay in taking out the Section 182 Summons, nor evidence that the
Respondents have suffered any prejudice as a result of the delay (if any).
90. In respect of the Respondents’ challenge to the Retention
Monies Payment Order[25], the Liquidators have
not filed any respondent’s notice to challenge the Judge’s finding that a trust exists over the Retention Monies
in favour of the Respondents. On the basis of this finding by the Judge, the payment of the Retention
Monies by the Employer to the Respondents should not be regarded as constituting any disposition of the
Company’s property, and thus s 182 has no application to such payment. Further, as at the date of the
hearing before the Judge, the Liquidators’ position was that they were not yet in a position to ascertain or
finalise the quantum of any set-off, and the exact quantum of the set-off might crystalise only after the final
account for the Project had been finalised between the Employer and the Liquidators, but no approximate
timeframe was provided[26]. While the Liquidators
have made some general assertions of potential set-offs and estimated quantum of such set-offs[27], the Liquidators have not produced any concrete evidence
in support of those assertions. Thus, even though the Company has, in theory, a contractual right of set
off, we do not see that the Liquidators have shown a prima facie case that any set-off exists on the
facts. There is certainly no finding by the Judge of any such prima facie case. To order
the Retention Monies to be paid to the Liquidators to be held in separate trust accounts pending finalization of
the final account between the Employer and the Company would effectively be giving the Liquidators security, or
at least a measure of preservation of the Respondents’ assets, to satisfy potential claims which may never
materialise, or may be entirely unfounded. Since the Retention Monies belong to the Respondents
beneficially and have in fact been paid to the Respondents, and no prima facie case has been shown that
the Liquidators have got any valid claim of set-off on the facts, we do not consider that there is any
sufficient justification to order the Respondents to pay the Retention Monies to the Liquidators.
THE 3RD RESPONDENT’S APPLICATION TO AMEND ITS NOTICE OF APPEAL
91. The main argument that the 3rd Respondent
wishes to raise by way of amendment to its notice of appeal is that, even if the Court should find that the
Payments are caught by s 182, the Court ought nevertheless to exercise its residual discretion “to order the
Liquidators not to enforce their legal rights” under s 182 in reliance upon the “rule” in Ex parte
James. That rule has been described as being an “elusive and difficult principle based on
morality”. It has also been said that a trustee for creditors may be restrained from enforcing a
claim under the rule in Ex parte James if “it were not honourable – if it were not high minded – if it
would be contrary to natural justice – if it would be shabby – if it would be a dirty trick for him to
retain it – or … if to do so would be inconsistent with natural justice and that which an honest man would
do”: see Re Ng Shiu Fan [2009] 4 HKLRD 774 (CA), at §30.
92. In Re Ng Shiu Fan [2008] 4 HKLRD 813 (CFI), at §75,
Kwan J (as she then was) referred to Williams and Muir Hunter on Bankruptcy (19th ed,
1979), at page 249, where it was stated that “it is not easy to define the exact bounds of a principle based
upon the control exercised by the court over its officer, which, since it operates in fields not covered by
the established rules of law and equity, is incapable of reduction to an exact formula and must in its
application be governed in part by ethical considerations.”.
93. For the present purpose, it is not necessary for us to
determine the exact boundary of the principle, or rule, in Ex parte James. In our view, the short
answer to the 3rd Respondent’s argument is that, if the Payments were caught by s 182, it would be
entirely proper for the Liquidators to take action to seek recovery of the Payments for the benefit of the
general body of creditors of the Company, consistently with the pari passu principle underlining our
insolvency legislation. We do not see how it can sensibly be argued that the conduct of the Liquidators,
when they take action to recover assets belonging to the Company, is “not honourable”, or “not high minded”, or
“contrary to natural justice”, or “shabby”, or amounts to “a dirty trick”, or is “inconsistent with natural
justice and that which an honest man would do”. The 3rd Respondent’s attempt to rely on the
rule in Ex parte James in the present context is misconceived. There is also force in Ms Eu’s
argument that the 3rd Respondent should not be permitted to advance the Ex parte James
point for the first time in the Court of Appeal since it is fact-sensitive and was not explored below: see
Flywin Co Ltd v Strong & Associates Ltd (2002) 5 HKCFAR 356, at §38.
94. The other proposed amendments to the 3rd
Respondent’s notice of appeal are either insignificant, or non-essential (such as seeking an order that the
money paid into court as security for costs be returned to the 3rd Respondent), or assertions
unsupported by evidence (such as the statement that “the Respondents had acted under a mistaken belief that
the direct payments to be made by the Employer could avoid s.182 even when the payments were made after the
presentation of a winding up petition”).
95. In all, the 3rd Respondent’s application to
amend its notice of appeal is refused.
DISPOSITION
96. The Respondents’ appeals are allowed, the Order dated
17 March 2025 is set aside, and the Section 182 Summons is dismissed. The 3rd Respondent’s
summons dated 20 February 2026 is also dismissed.
97. On the issue of costs, we make an order nisi that:
(1) The Respondents shall have the costs of the proceedings below, including the costs of the
hearing before the Judge.
(2) The 1st and 2nd Respondents shall have 60% of the costs of their appeal,
taking into account the grounds of appeal which have been rejected by the Court (including the jurisdiction
point).
(3) The 3rd Respondent shall have 80% of the costs of its appeal, taking into account
the grounds of appeal which have been rejected by the Court.
(4) The Liquidators shall have the costs of the 3rd Respondent’s summons dated 20
February 2026.
(5) All the above costs are to be taxed if not agreed, with certificate for 2 counsel.
The above costs order shall become absolute unless an application is made to vary the same within 14 days after
the date of this Judgment.
(Aarif Barma)
Vice President |
(Godfrey Lam)
Justice of Appeal |
(Anderson Chow)
Justice of Appeal |
Ms Audrey Eu SC leading Mr John Hui, instructed by DeHeng Law Offices (Hong Kong) LLP, for the Applicants
Mr Jonathan Chang SC leading Mr Martin Ho, instructed by Cocking & Co LLP, for the 1st and
2nd Respondents
Mr Jason Wong, Mr Esmond Wong and Ms Myranda Lai, instructed by Eric Yu & Co., for the 3rd
Respondent
[1] Save and except certain portions of the Payments
referred to as the “Retention Monies” which the Judge considered were trust monies of the Respondents but
subject to the Company’s potential right of set off (to be ascertained).
[2] After practical completion of the Project on 2
October 2018 and after the commencement of the winding up of the Company on 5 November 2018.
[3] See §7.2 of the Decision.
[4] See SCC-22(1)(a) of the Special Conditions of
Contract.
[5] See SCC-22(1)(b) of the Special Conditions of
Contract.
[6] See §19 of the Decision.
[7] The Supplementary Agreement entered into on 12
May 2017 was in fact the second supplementary agreement which varied or modified the terms of the Main
Contract. There was an earlier supplementary agreement entered into by the Employer and the Company
dated 10 March 2017, and a subsequent supplementary agreement dated 14 February 2018.
[8] See §§24.3 and 25 of the Decision.
[9] See §49.1-49.3 of the Decision.
[10] The 1st and 2nd
Respondents applied for a validation order on 14 April 2025 after the date of the Decision, but the
application was subsequently dismissed by consent on 9 May 2025.
[11] Ground 1 of R3 NOA is simply a general
statement that the Judge ought to have found that “the payments made by the Employer to the Respondents
after the commencement of the winding up of the Company were not caught by s.182 of the Companies (Winding
Up and Miscellaneous Provisions) Ordinance, Cap.32.”.
[12] See §6(a) of the 3rd Respondent’s
draft amended notice of appeal.
[13] See [2019] 3 HKLRD 367, at §§1 and 2.
[14] That case also concerned a summons issued by
the liquidator of a company for a declaration that two payments made after the commencement of winding up
were void under s 227 of the Companies Act 1948 (equivalent to s 182 of the Ordinance), and for an order for
the recovery of the relevant sums from the recipient.
[15] See §20 of the Skeleton Submissions for the
1st and 2nd Respondents dated 20 February 2026.
[16] See fn 7 above.
[17] See §§7 to 21 of the Skeleton Submissions
for the 3rd Respondent dated 20 February 2026.
[18] See §12 of the Skeleton Submissions for the
3rd Respondent.
[19] See Decision, at §29.
[20] See Grounds 2 & 3 of R1-2 ANOA and
Ground 4 of R3 NOA.
[21] See Ground 4 of R1-2 ANOA and Ground 5 of R3
NOA.
[22] See Ground 6 of R3 NOA.
[23] See §27.1 of the Decision.
[24] See §48 of the Decision. The
1st and 2nd Respondents’ subsequent application for a validation order was dismissed
by consent on 9 May 2025.
[25] See Ground 5 of R1-2 ANOA and Ground 7 of R3
NOA.
[26] See §57.1-57.3 of the Decision.
[27] See §§32(3)-33 of the 8th
Affirmation of Osman Mohammed Arab filed on 9 July 2024, and §20(5) of the 12th Affirmation of
Osman Mohammed Arab filed on 12 November 2018.
|