BUDA PIPE REHAB ENG CO LTD v. CPC CONSTRUCTION HONG KONG LTD, HCCT 69/2018
Case Number
HCCT 69/2018
Court
Court of First Instance
(CFI)
Decision Date
22 February 2019
Parties
Applicant(s):

BUDA PIPE REHAB ENG CO LIMITED (formerly known as “BUDA PIPE REHABITATION & ENGINEERING COMPANY LIMITED)

Respondent(s):

IN THE MATTER OF THE ARBITRATION ORDINANCE, CAP 609 ______________ ____________ BETWEEN BUDA PIPE REHAB ENG CO LIMITED (formerly known as “BUDA PIPE REHABITATION & ENGINEERING COMPANY LIMITED) Plaintiff (Respondent in the Arbitration) and CPC CONSTRUCTION HONG KONG LIMITED

For Applicant(s):

Mr Tony Ng, instructed by K M Tang & Co

For Respondent(s):

Mr Jonathan Wong

BUDA PIPE REHAB ENG CO LTD v. CPC CONSTRUCTION HONG KONG LTD

[2019] HKCFI 503

Court of First Instance22 February 2019

Citation

Court

Procedural posture

Issues

Holdings

Legal principles

Disposition