Case Details
Citation
BUILDWELL CONSTRUCTION CO LTD v. MAK KWOK WAI t/a WILLEY CONSTRUCTION AND ENGINEERING CO, HCA 1007/1987
Case Number
HCA 1007/1987
Court
Court of First Instance
(CFI)
Decision Date
10 June 1987
Parties
Applicant(s):

BUILDWELL CONSTRUCTION COMPANY LIMITED

Respondent(s):

MAK KWOK WAI trading as WILLEY CONSTRUCTION & ENGINEERING COMPANY

For Applicant(s):

He then wrote to the plaintiffs' solicitors explaining that there had been a mistake and requesting an extension of a further seven days for the filing of the defence. The defendants' solicitors replied to that saying that they could not grant such an extension as they had already applied for judgment by default. A certificate that no defence had been filed by the defendants was filed by the solicitors; In both of these cases however, the parties had laid down a date for the doing of something, failing which, judgment could be entered. Clearly there was an agreement between the parties that if there was failure to comply with that requirement, the plaintiffs were at liberty to enter judgment. Here, however, there was simply an extension of time for filing a defence. Mr Lai who appears

For Respondent(s):

by the plaintiffs with both those requirements. The decision made by the Master was that leave was granted to extend the filing of the defence to the 30th April and that the plaintiff should have costs of the hearing. There is no note as to whether this was done by consent and there is no reference to the request for the production of documents or for the further and better particulars. At this hearing Mr King

BUILDWELL CONSTRUCTION CO LTD v. MAK KWOK WAI t/a WILLEY CONSTRUCTION AND ENGINEERING CO

HCA 1007/1987

Court of First Instance10 June 1987

Citation

Court

Procedural posture

Issues

Holdings

Legal principles

Disposition

Key citations